RaceRocks.com
Videocams Ecosystems History First nations Sponsors
Management Home
ENERGY
BATTERIES ARE INSTALLED. March 2006
Tidal Energy Project
Weather
Live Video
Archives
Technology
workmarch1306s.jpg mar23racks.jpg mar23rack3s.jpg
New electrical wiring is extensive in the Enregy Centre The lower rack of batteries are installed
mar23rackcloses.jpg mar23placebattery.jpg mar23lastracks.jpg
A moveable winch is mounted to guide in the upper layer of batteries. There are 95 batteries each weighing 112 Kg.
albattery
Alex Chan (PC yr 32) checking on the installed batteries.
Return to the Schedule and Log Index for various phases of the Project.
clean current

Return to: Launch of the Project at Pearson College,

racerocks.com home page
Sitemap Contact
webmaster:
Garry Fletcher
Copyright